Narayanghat-Muglin street area gets new due date for consummation

Tukhabar Correspondent
March 22nd, 2018

Chitwan, – The due date for the development of Narayanghat-Muglin street segment has been stretched out by three months more.

The development organizations were campaigning for expansion of the development due date refering to they were not inspiring time to work for various reasons.

Architect of Narayanghat-Muglin Road Project Shiva Khanal said that the due date for first area is till May 10 while the due date for second segment is May 20. In like manner, the third area has the due date of May 30, 2018.

The development organization was granted the development work in April 2015 to finish the task in two years. In any case, the due date was expanded refering to quake, India’s barricade and flooding for two successive years.

The Department of Roads on Wednesday endorsed the demand by the Project for date expansion which was finished in February.